| FRN: |
1799043032
|
| Billed Entity Name: |
Wichita Falls Independent School District
|
| Billed Account Administrator: |
Curtis Shahan |
| Applicant Type: |
School District |
| SPIN: |
143023855 |
| Service Provder Name: |
Zayo Group, LLC |
| 470 Application: |
170053841 |
| 471 Application: |
171020063 |
| 471 Review Status: |
FCDL Issued |
| 471 Contact Name: |
Ashley Brown |
| 471 Service Start Date: |
7/1/2017 |
| FCDL Date: |
1/13/2018 |
| Revised FCDL Date: |
|
| FCDL Comment for FCDL: |
|
|
486 Service Start Date: |
07/01/2017 |
| SPAC Filed?: |
True |
| FRN Nickname: |
Leased Dark Fiber Wan |
| FRN Status: |
Funded |
| Wave: |
34 |
| Appeal Wave Number: |
|
| FCDL Comment: |
MR1:The Recipients of Service 87756 Denver Alternative, 231219 Rosewood Head Start, 16029105 Northwest Head Start, 16029107 WF JJAEP, 16050233 Scotland Park Elem, 16050235 Southern Hills, 16057307 Farris Early Childhood Center, 16085374 North Texas State Hospital were removed from FRN Line Item 1799113434.001 to agree with the applicant documentation.||MR2:The FRN was modified from $1,905,845.96 to $1,334,203.46 to agree with the applicant documentation.||MR3:The State Match Amount was modified from $190,589.60 to $133,420.35 to agree with the applicant documentation.||MR4:The Total Route Feet and Average Cost per Foot of Outside Plant was modified from 1,177,440 feet and $1.62/foot to 98,918 feet and $13.49/foot to agree with the applicant documentation.||MR5:Per FCC Order 14-189, to prevent warehousing of excess fiber capacity, applicants may only receive funding for special construction charges for Leased Lit Fiber or Leased Dark Fiber if it is lit within the same funding year. If excess strands are being installed that will not be lit during the current FY and will be used by an ineligible entity or for an ineligible purpose; the applicant must provide a cost allocation for any variable costs of installing a higher strand cable as opposed to installing the strands needed just for the applicant’s exclusive use. The amount of the funding request was changed from $1,334,203.46 to $1,261,300.76 to remove $72,902.70 associated with ineligible excess fiber capacity. |
| FRN Service Type: |
Data Transmission and/or Internet Access |
| Site ID: |
|
| Contract Award Date: |
5/10/2017 12:00:00 AM |
| Contract Exp or Svc End Date: |
6/30/2027 |
| Last Date To Invoice: |
2/26/2019 |
| FRN Committed Amount: |
$1,127,855.14 |
| Total Authorized Disbursement: |
$1,127,855.14 |
| Undisbursed Amount: |
$0.00 |
| Invoicing Mode: |
SPI |
- BEN:
-
140959
- County District #:
-
243905
- Region:
- 9
- Funding Year:
- 2017
|
Original
Request |
Committed
Request |
| Total Monthly Cost |
$0.00
|
$0.00
|
| Months of Service |
12
|
12
|
| Annual Recurring Charges |
$0.00
|
$0.00
|
| Total One Time Eligible Cost |
$1,905,845.96
|
$1,261,300.76
|
| Total One Time Ineligible Cost |
$0.00
|
$72,902.70
|
| Total One Time Cost |
$1,905,845.96
|
$1,334,203.46
|
| Total Cost |
$1,905,845.96
|
$1,261,300.76
|
| Discount |
90
|
89.42
|
| Funding Requested Amount |
$1,715,256.36
|
$1,127,855.14
|